Casablanca Municipal Action Plan (PAC) 2023-2028

Within a consortium with Inetum Consulting Maroc, SUD prepared the Casablanca Municipal Action Plan 2023-2028: MAD 39.6 billion, six pillars, 99 projects, adopted on 18 May 2023.

Casablanca needed an action plan for 2023-2028: an investment programme settled, ranked and financeable, at the scale of sixteen districts and 384 km². SUD — Sciences Urbaines et de Développement carried out this assignment within a consortium with Inetum Consulting Maroc, selected following a tender. The plan was adopted by the Municipal Council on 18 May 2023.

Assignment record
Commissioning authority Municipality of Casablanca
Assignment Preparation of the Municipal Action Plan 2023-2028
Consortium Inetum Consulting Maroc – SUD
Selection Municipal tender, April 2022
Adoption 18 May 2023, ordinary session of the Council
Scope 16 districts, 384 km²
Legal framework Organic Law no. 113-14 on municipalities

The challenge: programming a metropolis, not a city

The Municipal Action Plan is a legal obligation: Organic Law no. 113-14 requires every municipality to set, for the duration of the term, its priorities for facilities, services and investment. The exercise is codified and practised everywhere in Morocco. In Casablanca, it changes in nature.

Sixteen districts, 384 km², the densest population and economic activity in the Kingdom, and a previous plan — that of 2016-2021 — which had run its course. Each district arrives with its own needs, all of them legitimate, whose sum far exceeds what the municipality can commit to. The difficulty is therefore not listing projects: it is choosing between them, ordering them over time, and keeping only what can actually be funded.

Selected through a competitive tender

In April 2022, the Municipality of Casablanca selected the consortium formed by Inetum Consulting Maroc and SUD to prepare its Municipal Action Plan. Le Desk, which revealed the selection, notes that the consortium won against Mazars, Fidaroc Grant Thornton, Valyans, SIS Consultants and Conseil Ingénierie et Développement (CID) — a field that indicates the level of the competition.

The method: a twofold approach, participatory and analytical

The adopted document itself describes the methodological choice: the preparation of the PAC “therefore rests on a twofold approach: participatory, through the involvement of the various stakeholders, and analytical, by drawing on the territory’s reference documents”.

The analytical strand drew on more than 220 documents — including the previous Municipal Action Plan 2016-2021, regulatory texts, sector strategies and the territory’s statistical data — as well as fifteen experts specialising in the municipality’s fields of competence, and a benchmarking exercise against major Moroccan cities and comparable international metropolises.

The participatory strand was conducted at a scale unusual for a municipal document.

8 thematic workshops bringing together more than 300 stakeholders

45 interviews and focus groups with more than 200 participants — districts, prefectures, local development companies, service concessionaires and civil society

More than 3,300 citizens expressed their needs and priorities through a digital consultation platform

8 standing committees organised by field

It is this articulation that makes the difference between a list of facilities and a strategy: the consultation produces the priorities, the analysis produces the trade-offs, and the financial programming makes the whole thing executable.

From diagnosis to programming

Consultation on this scale produces a considerable, and contradictory, body of material. Moving from thousands of requests to a workable programme requires three distinct operations: ranking, sequencing, funding.

Ranking resulted in six pillars, broken down into twenty-four programmes and ninety-nine projects. Sequencing distributed them over time: commit first to what is ready and to what unlocks the rest, defer what depends on permits, land or co-funding still to be secured.

The third strand is the least visible and the one that decides everything. The municipality carries only part of the budget; the rest rests on a round table of partners. An action plan without a funding structure remains a catalogue of intentions — that is the dividing line between a document adopted and a document applied.

The outcome: an adopted plan

39,6
billion dirhams
budget of the adopted plan
6
development pillars
from the living environment to resources
24
programmes
breaking down the pillars
99
projects
in the adopted version

The vision adopted — “Casablanca, a sustainable and attractive metropolis serving its citizens” — breaks down into six pillars, whose budget allocation sets out the order of priorities.

Pillar Budget
A modern city, with high-level infrastructure serving territorial development MAD 30.34 billion
A smart and sustainable city MAD 4.50 billion
An inclusive city, serving the wellbeing of all its citizens together MAD 2.33 billion
A lively and culturally rich city MAD 2.26 billion
A city with strengthened human, technical and financial resources MAD 182 million
A metropolitan city open to the world MAD 108 million

More than three quarters of the budget goes to infrastructure. This is not a lack of ambition for the rest: it is the recognition that in Casablanca, mobility, networks and sanitation condition everything else.

A contribution recorded in the document itself

The Municipal Action Plan published by the Municipality of Casablanca carries a mention of the consortium in its source apparatus, notably under the sector analyses:

« Source : Ministère de la Transition énergétique, analyse groupement Inetum Consulting-SUD »

The mention recurs several times in the document. It is the most solid form of reference available to a consulting firm: not a press mention, but an attribution by the commissioning authority itself, in a public and lasting document.

The team

Eight specialisms were brought together on the assignment, three of which bear specifically on funding and monitoring — the part of the work that determines whether an action plan stays a document or becomes a programme that is carried out.

  • Project director
  • Municipal planning specialist
  • Territorial economist
  • Local finance specialist
  • Financial structuring specialist
  • Monitoring and evaluation specialist
  • Statistician
  • Cartographer

What the assignment shows

The Casablanca PAC belongs to a series of planning assignments carried out by SUD at different scales.

In April 2022, the same Inetum – SUD consortium was selected by the Oriental Regional Council to prepare the Regional Development Programme 2022-2027, for a value of around three million dirhams: diagnosis of economic potential, programming of actions, identification of implementation partners.

In December 2021, the National Agency for the Development of Oasis and Argan Zones commissioned SUD to prepare the 2022-2030 national strategy for those territories, for MAD 3.8 million.

In 2017, SUD prepared the Fès-Meknès Regional Territorial Development Plan, an exercise in recasting the directions of three merged former regions. Earlier, the Ziz Valley Urban Development Master Plan, approved in Official Bulletin no. 5786 of 2 November 2009, carries the firm’s name in the signature block of its presentation report published by the Errachidia-Midelt Urban Agency.

Further reading

Our press review of Médias24’s coverage of the Municipal Action Plan, and of the figures in the preparatory version presented in February 2023.

Médias24 on the Casablanca PAC

Sources — Casablanca Municipal Action Plan
  1. Municipality of Casablanca, Plan d’Action de la Commune de Casablanca 2023-2028, full French version — casablancacity.ma. Pillars, programmes, projects, methodology and mention of the consortium.
  2. Souleiman Ketti, « Nabila Rmili s’appuiera sur Inetum pour son Plan d’Action de la Commune », Le Desk, 15 April 2022 — ledesk.ma. Selection of the consortium and list of competitors.
  3. Kenza Khatla, « Casablanca : le Plan d’action communal 2023-2028 enfin prêt ! », Médias24, 27 February 2023 — medias24.com. Preparatory version of the plan.
  4. « Casablanca : le Conseil communal approuve le PAC 2023-2028 (39,6 MMDH) », H24info, 19 May 2023 — h24info.ma. Adoption and final budget.
Other assignments cited
  1. Yahya Benabdellah, « Oriental : l’élaboration du PDR confiée à Inetum et Bet-Sud », Médias24, 19 April 2022 — medias24.com.
  2. Soufiane Sbiti, « Pour 3 MDH, Abdenbi Bioui confie l’élaboration du PDR de l’Oriental au cabinet Inetum », Le Desk, 19 April 2022 — ledesk.ma.
  3. Saïd Naoumi, « Zones oasiennes et arganier : le cabinet BET-Sud chargé d’élaborer la nouvelle stratégie 2022-2030 », Le Matin, 15 December 2021 — lematin.ma.
  4. Souleiman Ketti, « 50 000 hectares d’arganier d’ici 2030 : un bureau d’études recruté pour élaborer la stratégie », Le Desk, 13 December 2021 — ledesk.ma.
  5. « Fès-Meknès : Le SRAT pour juillet », Les Eco, 19 June 2017 — leseco.ma.
  6. Errachidia-Midelt Urban Agency, Schéma Directeur d’Aménagement Urbain de la vallée du Ziz — rapport de présentation, approved in Official Bulletin no. 5786 of 2 November 2009 — auer.gov.ma.