The Oriental region needed a development programme for 2022-2027: a diagnosis, a ranked programme and a funding structure capable of correcting two entrenched divides — between the north and the south of the region, and between its urban and rural areas. SUD carried out this assignment within a consortium with Inetum Consulting Maroc. The programme was adopted unanimously on 6 March 2023.
| Commissioning authority | Oriental Regional Council |
|---|---|
| Assignment | Preparation of the Regional Development Programme 2022-2027 |
| Consortium | Inetum Consulting Maroc – SUD |
| Award | April 2022, following a tender |
| Value | Around MAD 3 million |
| Contractual timeframe | 190 days |
| Adoption | 6 March 2023, ordinary March session, unanimously |
| Legal framework | Organic Law no. 111-14 on regions |
The challenge: a two-speed region
The Oriental presents a difficulty that few Moroccan regions face to this degree: a marked gap between its northern and its southern parts, compounded by a gap between urban and rural areas. Both divides are written into the terms of reference as the very object of the programme.
A regional development programme is not a catalogue of projects. It is the instrument through which a region makes its choices: which areas to bring up to standard first, which projects to commit to first, and with which partners to fund them. In the Oriental, those choices concerned a territory whose two halves do not advance at the same pace.
The brief: three tasks, 190 days
The Regional Council launched its procurement in February 2022, at an estimated cost of MAD 3.84 million, with bid opening set for 27 March and a delivery period of 190 days. The contract was awarded in April to the Inetum Consulting Maroc – SUD consortium, for a value of around three million.
The terms of reference came in three tasks. First a diagnosis “bringing out the economic, social, cultural and environmental potential of the region”. Then the preparation of the RDP 2022-2027 and of its implementation strategy, broken down into operational actions. Finally — and this is the part that determines whether the programme is applied — the definition of a draft State-region programme-contract, the preparation of the specific agreements and the setting up of an implementation mechanism.
The method: going down into the provinces
Between the award and the adoption, the Council held thematic workshops and territorial consultations at the level of the region’s prefectures and provinces, as well as meetings with central, regional and provincial authorities and with local stakeholders.
This fieldwork is not incidental in a region this large and this contrasted. A diagnosis written from Oujda does not see the same priorities as a workshop held in Figuig or Driouch. It is the provincial consultation that makes it possible to rank priorities without choosing blind.
The outcome: 19.5 billion, 21 projects
The adopted programme carries a budget of 19.475 billion dirhams, of which the Regional Council funds 4.550 billion and partners 14.925 billion. It breaks down into 21 main projects across four areas:
| Area | Projects | Total cost |
|---|---|---|
| Cross-cutting | 5 | MAD 8,590 million |
| Social | 5 | MAD 4,460 million |
| Economic | 7 | MAD 4,220 million |
| Environmental | 4 | MAD 2,205 million |
The funding breakdown is the most telling piece of information in the programme: the Regional Council carries less than a quarter of the budget. The other three quarters depend on partners who had to be identified and brought under agreement — which was precisely the third task in the terms of reference.
The programme rests on five strategic pillars: equitable development serving the whole region, with solidarity towards vulnerable areas; a region established as a high value-added economic hub; economic growth that benefits all citizens; an enhancement of cultural and natural heritage that respects regional specificities; and an ecologically responsible territory.
The team
Five specialisms were brought together on the assignment, with territorial governance ranked alongside the diagnosis — a regional programme is only worth the partners it manages to commit.
- Project director
- Urban and regional planner
- Economist
- Sociologist
- Territorial governance specialist
What the assignment shows
The Oriental RDP belongs to a series of planning assignments carried out by SUD at different scales. The same Inetum – SUD consortium had been selected shortly before to prepare the Casablanca Municipal Action Plan 2023-2028. Five years earlier, SUD prepared the Fès-Meknès Regional Territorial Development Plan on its own.
Municipality, region, national scale: the exercise is the same each time. Turning a territorial diagnosis and a consultation process into programming that is ranked, sequenced and financeable, and that the commissioning authority can actually commit to.
Our press review of the award of the RDP, as Médias24 announced it in April 2022.
- Oriental Regional Council, « La stratégie du Conseil pour le développement de la Région de l’Oriental » — conseilregionoriental.ma. Budget, funding breakdown, 21 projects and strategic pillars.
- Kenza Khatla, « La région de l’Oriental prépare son nouveau PDR pour 2022-2027 », Médias24, 28 February 2022 — medias24.com. Tender, estimated cost, timeframe and tasks.
- Yahya Benabdellah, « Oriental : l’élaboration du PDR confiée à Inetum et Bet-Sud », Médias24, 19 April 2022 — medias24.com. Award to the consortium.
- Soufiane Sbiti, « Pour 3 MDH, Abdenbi Bioui confie l’élaboration du PDR de l’Oriental au cabinet Inetum », Le Desk, 19 April 2022 — ledesk.ma.
- « مجلس جهة الشرق يصادق على مشروع برنامج التنمية الجهوية 2022-2027 », 7 March 2023 — pam.ma. Adoption on 6 March 2023, territorial consultation.
Other assignments cited
- Municipality of Casablanca, Municipal Action Plan 2023-2028 — see our case study on the Casablanca PAC.
- Fès-Meknès Region, Regional Territorial Development Plan 2017-2042 — see our case study on the Fès-Meknès SRAT.