The Tanger-Tétouan-Al Hoceïma region needed a regional territorial development plan: the document that sets out, for twenty-five years, the spatial organisation of a territory and the ranking of its projects. SUD won the tender issued by the Regional Council. The plan was adopted on 13 January 2021, unanimously by the members present.
| Commissioning authority | Tanger-Tétouan-Al Hoceïma Regional Council |
|---|---|
| Assignment | Preparation of the Regional Territorial Development Plan 2021-2046 |
| Decision to launch | Ordinary session of March 2018 |
| Procedure | Tender issued by the Regional Agency for Project Implementation |
| Start of work | 27 March 2019, Fahs-Anjra prefecture |
| Adoption | 13 January 2021, extraordinary session, unanimously by the members present |
| Horizon | 2021-2046 |
| Legal framework | Organic Law no. 111-14 on regions |
The challenge: a pivotal region
Tanger-Tétouan-Al Hoceïma is not a region like the others. It brings together the leading port of the Mediterranean, a rapidly growing industrial base, a double coastline — Atlantic and Mediterranean — and, within the same perimeter, a Rif hinterland among the most isolated in the Kingdom.
A regional territorial development plan is not an investment programme. It is the level above: the document that decides where the region wants to concentrate its growth, which areas it intends to open up, and in what order. The successive regional development programmes then attach to it. The horizon is long — twenty-five years — precisely because the organisation of a territory cannot be corrected within a single term of office.
The brief: a decision, then a wait
The Regional Council approved the principle of the study at its ordinary session in March 2018, then issued the tender through its Regional Agency for Project Implementation. SUD won it.
A year passed between that decision and the effective start of work. The chair of the Council’s territorial planning committee, Leila Azerkane, explained it publicly: the delay in publishing the regulatory texts governing the exercise, then the procedures and timescales inherent in the Council’s own decision and in the tender.
This point is rarely brought into the debate, and it deserves to be. A consulting firm does not control the upstream timetable of a public commission. What it does control is delivering within the window that remains.
The method: a committee, then the field
Work was launched on 27 March 2019 at the headquarters of the Fahs-Anjra prefecture, with the first meeting of the regional SRAT committee, chaired by the region’s wali, Mohamed Mhidia. The watchword adopted for the exercise — “the future is not forecast, it is built” — says enough about the intention: a forward-looking plan, not an extrapolation of trends.
The sequence is that of any assignment of this nature, and it is the consultation that gives it its value. A regional diagnosis written from Tangier does not rank the same priorities as a workshop held in Chefchaouen or Al Hoceïma. The work consists in bringing those divergences to the surface, then settling them explicitly rather than by default.
The outcome: 376 projects, 291.6 billion
The Regional Council adopted the SRAT 2021-2046 on 13 January 2021, in extraordinary session, unanimously by the members present. The plan retains 376 projects assessed as feasible, for a total investment of 291.6 billion dirhams across the whole horizon.
The same session adopted a programme-contract with the State covering the priority projects of the 2020-2022 regional development programme: 21 projects, MAD 4.399 billion, committing ten ministerial sectors, five public bodies, the Regional Council and the Wilaya. Its breakdown shows how a long-term plan translates into dated commitments:
| Programme-contract strand | Projects | Amount |
|---|---|---|
| Competitiveness and attractiveness | 6 | MAD 1,654 million |
| Sustainable development | 8 | MAD 787.21 million |
| Social and territorial cohesion | 7 | MAD 1,958 million |
A distinction to make. The SRAT and this programme-contract are two different instruments, adopted on the same day. The first sets the framework for twenty-five years; the second commits the State and the region for three years under the regional development programme. The amounts are not cumulative.
Published as open data
The study documents have been published by the Region on Morocco’s national open data portal, under an Open Database License, since 6 January 2022: the phase 3 presentation and the study file submitted to the Council session.
That is rare enough in this field to be worth noting. A regional plan published as open data is a plan that municipalities, project sponsors and researchers can actually use, instead of a document that stays in the Council’s archives.
The team
Twelve specialisms were brought together on the assignment, from metropolisation to rural development — the two extremes of a region that holds together an industrial hub of international rank and a Rif hinterland.
- Project manager
- Territorial planning specialist
- Environmental specialist
- Regional economics specialist
- Infrastructure and mobility specialist
- Metropolisation specialist
- Rural development specialist
- Statistician
- Demographer
- Institutional governance specialist
- Digitalisation specialist
- GIS and geomatics specialist
What the assignment shows
The Tanger-Tétouan-Al Hoceïma SRAT is the broadest of the planning assignments carried out by SUD: a twenty-five-year horizon, 376 projects, a pivotal region between an industrial hub of international rank and a hinterland still to be opened up.
It belongs to a continuous series. SUD prepared the Fès-Meknès Regional Territorial Development Plan, then the Oriental Regional Development Programme and the Casablanca Municipal Action Plan, in consortium with Inetum. Regional plan, regional programme, municipal plan: three scales, one and the same exercise — turning a territorial diagnosis and a consultation process into programming that is ranked, sequenced and financeable.
Our press review of the launch of the plan, as the northern press covered it in March 2019.
- Hayʾat at-tahrir, « الانطلاقة الرسمية لمسلسل إعداد التصميم الجهوي لإعداد التراب لجهة طنجة- تطوان- الحسيمة », Larache News, 28 March 2019 — larachenews.com. Award of the tender, the March 2018 decision, the launch of 27 March 2019, the regional committee and the wali.
- « ليلى أزرقان: التصميم الجهوي لإعداد التراب طموح للفاعلين بالجهة… », 28 March 2019 — pam.ma. The same despatch; Leila Azerkane’s remarks on the causes of the delay.
- « Conseil régional Tanger-Tétouan-Al Hoceïma : adoption du SRAT et d’un contrat-programme avec l’État », Le Journal de Tanger, 16 January 2021 — lejournaldetanger.com. Adoption on 13 January 2021, 376 projects, MAD 291.6 billion, details of the programme-contract.
- « Tanger-Tétouan-Al Hoceïma : adoption du SRAT et d’un contrat-programme avec l’État », MAP Express, 13 January 2021 — mapexpress.ma.
- Tanger-Tétouan-Al Hoceïma Region, « Schéma régional d’aménagement du territoire de la région Tanger-Tétouan-Al Hoceima 2021-2046 », national open data portal, 6 January 2022 — data.gov.ma. ODbL licence.
- Tanger-Tétouan-Al Hoceïma Region, « Etude – schéma régional d’aménagement du territoire Région Tanger-Tétouan-Al Hoceima 2021-2046 », national open data portal, 6 January 2022 — data.gov.ma.
Other assignments cited
- Fès-Meknès Region, Regional Territorial Development Plan 2017-2042 — see our case study on the Fès-Meknès SRAT.
- Oriental Region, Regional Development Programme 2022-2027 — see our case study on the Oriental RDP.
- Municipality of Casablanca, Municipal Action Plan 2023-2028 — see our case study on the Casablanca PAC.